Schedule

Phase 1
Phase 2
Phase 2: Building cable installation timeline
Cable Installation Schedule Start In Progress Complete
Studio Arts Center Fall 2026 √ -
700 S. Davis (Old PD) Fall 2026 √ -
Ground Warehouse Fall 2026 √ -
Military & Veterans Services Fall 2026 - -
Environmental Health & Safety West Fall 2026 - -
Amphibian & Reptile Diversity Research Building Fall 2026 - -
Woolf Hall Fall 2026 - -
University Administration Building (UAB) Spring 2027 - -
Texas Hall Spring 2027 - -
Preston Hall Spring 2027 - -
Carlisle Hall Spring 2027 - -
College Hall Spring 2027 - -
Nedderman Hall Spring 2027 - -
Fine Arts Building Spring 2027 - -
Environmental Health & Safety Spring 2027 - -
Aerodynamics Research Building Spring 2027 - -
Physical Plant Annex Spring 2027 - -