Schedule

Phase 1
Phase 2
Phase 2: Building cable installation timeline
Cable Installation Schedule Start In Progress Complete
Studio Arts Center 09/03/26 - -
UPB 700 S. Davis (Old PD) 09/08/26 - -
Ground Warehouse 09/11/26 - -
Military & Veterans Services 09/15/26 - -
Environmental Health & Safety West 09/18/26 - -
Amphibian & Reptile Diversity Research Building 09/22/26 - -
Woolf Hall 09/24/26 - -
University Administration Building (UAB) 10/22/26 - -
Texas Hall 11/19/26 - -
Preston Hall 12/01/26 - -
Carlisle Hall 12/08/26 - -
College Hall 12/17/26 - -
Nedderman Hall 12/22/26 - -
Fine Arts Building 02/05/27 - -
Environmental Health & Safety 03/11/27 - -
Aerodynamics Research Building 03/16/27 - -
Physical Plant Annex 03/19/27 - -