Schedule
Phase 1
- Completed Spring 2026
Phase 2
- Installations: Beginning Summer 2026
- Phase 2: Building cable installation timeline
- Installation dates subject to change. Timelines will be updated as needed.
- Phase 2: Building cable installation timeline
- Program closeout and documentation: Summer 2027
Phase 2: Building cable installation timeline
| Cable Installation Schedule | Start | In Progress | Complete | |
| Studio Arts Center | 09/03/26 | - | - | |
| UPB 700 S. Davis (Old PD) | 09/08/26 | - | - | |
| Ground Warehouse | 09/11/26 | - | - | |
| Military & Veterans Services | 09/15/26 | - | - | |
| Environmental Health & Safety West | 09/18/26 | - | - | |
| Amphibian & Reptile Diversity Research Building | 09/22/26 | - | - | |
| Woolf Hall | 09/24/26 | - | - | |
| University Administration Building (UAB) | 10/22/26 | - | - | |
| Texas Hall | 11/19/26 | - | - | |
| Preston Hall | 12/01/26 | - | - | |
| Carlisle Hall | 12/08/26 | - | - | |
| College Hall | 12/17/26 | - | - | |
| Nedderman Hall | 12/22/26 | - | - | |
| Fine Arts Building | 02/05/27 | - | - | |
| Environmental Health & Safety | 03/11/27 | - | - | |
| Aerodynamics Research Building | 03/16/27 | - | - | |
| Physical Plant Annex | 03/19/27 | - | - |