Current Status
7-2-20–
- Scope has been expanded from 130 rooms to 189 rooms.
- Infrastructure buildout for the installation of power and electrical drops started since 16 December 2019 and is now complete.
- Installation of digital signs has also been in progress since December 2019 and currently scheduled to be completed in June 2020.
- Campus rollout after infrastructure buildout has been in progress since December 2019 until July 2020.