installation schedule by room for march 2024
BUILDING | ROOM | DATE | COMPLETED? |
Fine Arts | 132B |
3/11-3/15 |
√ |
137 | 3/11-3/15 | √ | |
147/147A | 3/11-3/15 | √ | |
166 | 3/11-3/15 | √ | |
178 | 3/11-3/15 | √ | |
303A | 3/11-3/15 | √ | |
311 | 3/11-3/15 | √ | |
346 | 3/11-3/15 | √ | |
348A | 3/11-3/15 | √ | |
407 | 3/11-3/15 | √ | |
419 | 3/11-3/15 | √ |
installation schedule by room for march-august 2023
BUILDING | ROOM | DATE | COMPLETED? |
Fort Worth | 120/121 |
3/13/23 |
√ |
120/121/111 | 3/14/23 | √ | |
111/113/114 | 3/15/23 | √ | |
113/114 | 3/16/23 | √ | |
Pickard Hall | 205/206 | 3/13/23 | √ |
205/206 | 3/14/23 | √ | |
305/309 | 5/15-5/26/23 | √ | |
Science Hall | 226 | 3/14-3/15/23 | √ |
Fine Arts | 411/412 | 3/15-3/16/23 | √ |
404 | 5/15-5/26/23 | √ | |
Woolf Hall | 219 | 5/15-5/26/23 | √ |
Architecture | 109 | 8/14-8/18/23 | √ |
113 | 8/14-8/18/23 | √ | |
103E | 8/14-8/18/23 | √ |
installation schedule by building
BUILDING | DATE | COMPLETED? |
Architecture | ||
Civil Engineering |
||
Campus Center | ||
Chemistry & Physics |
||
Earth & Environmental |
||
Engineering Research Building |
||
Fine Arts | ||
Library | ||
Life Sciences Building | ||
Maverick Activities Center |
||
Nedderman Hall | ||
Physical Education Building |
||
Preston Hall | ||
Studio Arts Center | ||
Swift Center | ||
Science Hall | ||
Trinity Hall | ||
University Hall | ||
Woolf Hall |